View critical path status

Review the overall health of your programme’s critical path, including key tasks, milestones, and risk indicators.

Audience

This guide is designed for project manager.

Steps

Step 1: Open the programme dashboard

Navigate to your project’s main programme dashboard where the Critical Path Status widget is displayed amongst other widgets.

Open the programme dashboard

Step 2: Review overall critical path health

Look at the top of the widget to see the overall status indicator, including whether the critical path is on track, at risk, critical, or delayed, along with float days and risk item counts if shown.

Review overall critical path health

Step 3: Examine critical tasks

Scroll through the tasks section of the widget to see individual tasks, their start and end dates, duration in days, completion percentage, and whether they are marked as critical.

Examine critical tasks

Step 4: Check milestone statuses

Review the milestones list to see upcoming and completed milestones, along with their status such as pending, at risk, completed, or delayed.

Check milestone statuses

Step 5: Confirm data as-of date

Use the data date shown in the widget to understand how current the critical path information is before making programme decisions.

Confirm data as-of date