Use the Critical Path Summary widget to quickly understand schedule float, critical activities, upcoming milestones, and overall programme risk.

Audience

This guide is designed for project manager.

Steps

Step 1: Open the dashboard containing the Critical Path Summary widget

Navigate to the relevant PlanOps dashboard where the Critical Path Summary widget has been added to view high-level programme schedule health.

Open the dashboard containing the Critical Path Summary widget

Step 2: Check the overall critical path risk indicator

Review the coloured risk label and icon at the top of the widget to see whether the programme is currently healthy, at risk, or in a critical state.

Check the overall critical path risk indicator

Step 3: Review total float on the critical path

Look at the total float days value to understand how much schedule contingency remains before key dates are impacted.

Review total float on the critical path

Step 4: See how many activities are on the critical path

Check the count of activities on the critical path to gauge how complex and sensitive your current programme path is.

See how many activities are on the critical path

Step 5: Identify the next critical milestone

Review the name, target date, and days remaining for the next critical milestone so you know which key event requires attention next.

Identify the next critical milestone

Step 6: Refresh the widget data

Use the widget refresh control, if available, to reload the data and ensure you are viewing the latest critical path status from the underlying programme.

Refresh the widget data