Step 1: Open a live plant record
Navigate to the plant register and open the record for a live item of plant that is currently on hire; the Off hire heading and button are shown only while the plant is still on hire.

Step 2: Review the off-hire prompt for overdue plant
If the expected off-hire date has already passed, review the warning message that highlights the expected off-hire date passed so you can prioritise taking this plant off hire.

Step 3: Start the off-hire process
Select the Off hire button to open the off-hire dialog, where you can confirm details and complete the off-hire for the selected plant item.

Step 4: Confirm plant is off-hired
After you complete the off-hire in the dialog and the plant stage changes to off hire or a demobilised date is recorded, the off-hire controls disappear so the plant can no longer be off-hired again.