View task dependencies on the Gantt chart
Use visual connector arrows on the Gantt chart to understand which tasks depend on each other and how work is sequenced.
This guide is designed for project manager.
Steps
Step 1: Open the programme Gantt chart
Navigate to the programme or project schedule view and open the Gantt chart so that tasks are displayed as horizontal bars on a timeline.

Step 2: Hover over a task to highlight its dependency chain
Move your cursor over a task bar to activate its dependency chain; the system highlights connector arrows for that task and its related predecessors or successors.

Step 3: Read the connector arrows between related tasks
Follow the highlighted elbow-shaped arrows, which run from the right edge of a predecessor task to the left edge of its dependent task, to see finish-to-start relationships between tasks.

Step 4: Compare positions of connected tasks on the timeline
Use the horizontal positions of the connected bars and arrows to understand whether a predecessor finishes before its dependent starts, and to spot any tasks that might constrain your schedule.

Step 5: Move to a different task to inspect another chain
Hover over another task bar to switch the active chain and view a different set of highlighted connectors without changing the underlying schedule.

Last updated: 2026-08-12