View live ITP status from the office
See live inspection progress on site for an ITP, including checklist completion, latest activity and any active hold points.
This guide is designed for project manager.
Steps
Step 1: Open the ITP detail view
Navigate to the ITP register, then select the ITP you want to review so that its detail view opens.

Step 2: Confirm the ITP is live on site
Check that the live status card appears at the top of the ITP detail; if no card is shown, the ITP has no field QR and is not yet live on site.

Step 3: Review checklist completion progress
In the live status card, review the checklist summary showing how many items are completed out of the total and the overall completion percentage.

Step 4: Check the most recent recorded activity
Look at the latest recorded item in the card to see who last recorded an inspection, when it was done, and whether it was "recorded on site" from a field session.

Step 5: Identify any active hold points
If there is a hold point awaiting a witness, review the highlighted section showing the hold point details and the date the witness was notified.

Step 6: Use relative and calendar dates for coordination
Use the relative times and formatted dates in the card (for example, "3 hours ago" and calendar dates) to coordinate with site teams and plan follow-up.