Delay Event – Client Instruction

Category: Contracts

Client instruction causing delay and you need to protect your contractual position? This task logs the delay event, issues immediate contractual notice to the client or contract administrator, reserves your rights, analyses the programme impact on the critical path, and generates a delay impact report linked to the event. The client is notified at each stage.

Input Parameters

ParameterTypeRequiredDescription
Client Instruction / Change DescriptionTextYesDescribe the client instruction or change that has caused or is likely to cause delay. Include wh...
Date of InstructionDateYesThe date the client instruction was issued or received.
Instruction Reference (Optional)TextNoAny reference number for the instruction (e.g. AI number, variation number, RFI reference, email ...
Affected Works / ActivitiesTextYesDescribe the works or programme activities affected by this instruction.
Estimated Delay (Working Days)TextNoYour initial estimate of the delay impact in working days (this will be validated against the pro...
Contract FormDropdownYesSelect the form of contract to ensure the correct notice provisions are referenced.
Specific Notice Clause (Optional)TextNoIf you know the specific clause requiring notice (e.g. NEC4 cl.61.3, JCT cl.2.27), enter it here....
Client / Employer OrganisationDropdownYesSelect the client or employer organisation from the project companies. The contractual notice wil...
Contract Administrator / Client Representative EmailTextYesEmail address of the contract administrator or client representative to receive the formal notice.
Additional Information (Optional)TextNoAny additional information, commercial concerns, or specific rights you wish to reserve.

Parameter Details

Contract Form

Select the form of contract to ensure the correct notice provisions are referenced.

Options:

  • nec4 - NEC4 ECC
  • nec3 - NEC3 ECC
  • jct-db-2016 - JCT Design & Build 2016
  • jct-sbc-2016 - JCT Standard Building Contract 2016
  • jct-mw-2016 - JCT Minor Works 2016
  • jct-ic-2016 - JCT Intermediate 2016
  • other - Other / Bespoke

Default: nec4

Outputs

Summary

Type: Text/Markdown

Summary

Outputs

Type: Structured Data (JSON)

Outputs

Event Id

Type: String

Event ID

Report Id

Type: String

Report ID

Completion Time

Type: String

Completion Time

Example Use Cases

Client Instruction Delay Notice

Record a delay event arising from a client instruction to change the facade specification.

Configuration:

  • Instruction Description: Change to facade cladding specification from aluminium to zinc
  • Instruction Date: 2026-03-15
  • Affected Works: External envelope and scaffolding programme
  • Estimated Delay: 3 weeks
  • Contract Form: jct_db

Tags: delay · client-instruction · contractual-notice · programme-impact · critical-path · compensation-event · extension-of-time