Log a delay caused by a client instruction and give notice

Category: Contracts

Records the delay, sends the contractual notice, reserves your rights, works out the programme impact and writes up the delay report.

Input Parameters​

ParameterTypeRequiredDescription
Client Instruction / Change DescriptionTextYesDescribe the client instruction or change that has caused or is likely to cause delay. Include wh...
Date of InstructionDateYesThe date the client instruction was issued or received.
Instruction Reference (Optional)TextNoAny reference number for the instruction (e.g. AI number, variation number, RFI reference, email ...
Affected Works / ActivitiesTextYesDescribe the works or programme activities affected by this instruction.
Estimated Delay (Working Days)TextNoYour initial estimate of the delay impact in working days (this will be validated against the pro...
Contract FormDropdownYesSelect the form of contract to ensure the correct notice provisions are referenced.
Specific Notice Clause (Optional)TextNoIf you know the specific clause requiring notice (e.g. NEC4 cl.61.3, JCT cl.2.27), enter it here....
Client / Employer OrganisationDropdownYesSelect the client or employer organisation from the project companies. The contractual notice wil...
Contract Administrator / Client Representative EmailTextYesEmail address of the contract administrator or client representative to receive the formal notice.
Additional Information (Optional)TextNoAny additional information, commercial concerns, or specific rights you wish to reserve.

Parameter Details​

Contract Form

Select the form of contract to ensure the correct notice provisions are referenced.

Options:

  • nec4 - NEC4 ECC
  • nec3 - NEC3 ECC
  • jct-db-2016 - JCT Design & Build 2016
  • jct-sbc-2016 - JCT Standard Building Contract 2016
  • jct-mw-2016 - JCT Minor Works 2016
  • jct-ic-2016 - JCT Intermediate 2016
  • other - Other / Bespoke

Default: nec4

Outputs​

Summary​

Type: Text/Markdown

Summary

Outputs​

Type: Structured Data (JSON)

Outputs

Event Id​

Type: String

Event ID

Report Id​

Type: String

Report ID

Completion Time​

Type: String

Completion Time

Example Use Cases​

Client Instruction Delay Notice​

Record a delay event arising from a client instruction to change the facade specification.

Configuration:

  • Instruction Description: Change to facade cladding specification from aluminium to zinc
  • Instruction Date: 2026-03-15
  • Affected Works: External envelope and scaffolding programme
  • Estimated Delay: 3 weeks
  • Contract Form: jct_db

Tags: delay · client-instruction · contractual-notice · programme-impact · critical-path · compensation-event · extension-of-time